Strengthen Equipment Maintenance and Upkeep to Ensure Stable Production Operations — Nanchang CNG Compressor 1,000-Hour Maintenance
“As the saying goes, ‘To do a good job, one must first sharpen one’s tools.’ Since completing their 8,000-hour maintenance in November 2020, all three CNG compressors in Nanchang have each accumulated 1,000 operating hours. To ensure the intrinsic safety of the equipment and to guarantee stable, smooth production, and to verify the results of the 8,000-hour maintenance, the Nanchang CNG Maintenance and Operations team recently carried out a 1,000-hour overhaul on all three compressors.
Prior to the project’s commencement, our company’s project team and the on-site maintenance and operations team conducted thorough consultations with the Nanchang Management Office and developed a maintenance plan, which was subsequently approved by the management office. In light of the challenges posed by pandemic‑related restrictions on vehicle access, and to ensure that users’ vehicles could be refueled without delay, the maintenance team adopted a strategy of “thorough preparation and meticulous execution, coupled with compact and efficient maintenance.” Accordingly, they carried out maintenance on three compressors over three consecutive mornings—April 6, April 7, and April 8.

Prior to the start of maintenance, the service team conducted a thorough review and preparation of tools, measuring instruments, and spare parts, thoroughly anticipated potential issues, and formulated corresponding solutions. Once maintenance commenced, tasks were clearly assigned, with each team member inspecting the components replaced during the 8,000-hour overhaul and successfully completing the 1,000-hour maintenance checklist.

It has been proven that thorough, meticulous, and comprehensive preparatory work is the key to securing decisive victory and enhancing operational efficiency. This approach also relies on the close collaboration of our company’s maintenance and operations team, thereby validating our guiding principle: unity is strength. During this round of maintenance and upkeep, the team not only successfully completed its tasks but also ensured that every employee fully recognized the importance and necessity of this work, bolstering both safety awareness and professional competence across the board. Our maintenance personnel demonstrated a strong spirit of resilience, dedication, and commitment, diligently carrying out maintenance activities to improve equipment performance and provide robust assurance for the safe and stable operation of our facilities going forward. The User Management Department and the station sites have expressed full appreciation and commendation for our field service team’s exceptional technical expertise and exemplary service attitude.