China’s east–west trunk gas pipeline network and north–south supply corridors have been fully interconnected.
On May 25, the Qingning Pipeline’s terminal station and the Xiqi Dongshu Qingshan Station interconnection project—key national infrastructure for oil and natural gas—was completed and put into operation, achieving full connectivity between China’s east–west trunk natural gas pipelines and its north–south supply corridors. This milestone further enhances the reliability of the natural gas transmission system in the Yangtze River Delta region and significantly strengthens the mutual backup and supply capabilities of natural gas resources across the Bohai Rim and the Yangtze River Delta, two major economic zones.
The project stretches from the Nanjing terminal of the Qingning Pipeline in the south to the Qingshan Station of the First West-to-East Gas Pipeline in the north, with a total pipeline length of 900 meters, a diameter of 1,016 millimeters, a design pressure of 10 megapascals, and a designed capacity of 12 billion cubic meters per year. Upon commissioning, the Qingshan Station of the First West-to-East Gas Pipeline will be fully interconnected with the Nanjing terminal of the Qingning Pipeline. Building on the earlier interconnections between the Qingshan Station and the Nanjing terminal of the Sichuan-to-East Gas Pipeline, as well as between the Nanjing terminals of the Qingning Pipeline and the Sichuan-to-East Gas Pipeline, this arrangement establishes a “triangular support” framework for mutual supply among the First West-to-East Gas Pipeline, the Sichuan-to-East Gas Pipeline, and the Qingning Pipeline. It also creates a gas-supply structure that enables seamless integration and mutual backup between onshore natural gas resources and overseas liquefied natural gas supplies, thereby effectively smoothing both domestic and international resource‑supply channels. At the same time, it leverages China’s regional pipeline network advantages in the Yangtze River Delta and North China, along with the emergency peak‑shaving capabilities of nearby gas storage facilities, to enhance the overall efficiency of natural gas utilization in these areas and further strengthen natural gas supply security. This initiative is of great significance in helping the central and eastern regions of China achieve their carbon‑peak and carbon‑neutral development goals more efficiently and at a faster pace.
The project officially broke ground on February 25, 2022, and was completed and commissioned in just 90 days. During construction, China National Pipeline Group thoroughly implemented General Secretary Xi Jinping’s new energy security strategy of “Four Revolutions and One Cooperation,” fully embraced the management philosophy of “integration of construction and operation,” and focused on achieving the goals of building a “safe pipeline, green pipeline, development‑oriented pipeline, and friendship‑based pipeline.” The project coordinated epidemic prevention and control with construction activities, worked tirelessly to overcome challenges such as complex underground utilities and a tight construction schedule, and minimized environmental impacts through innovative techniques like pipe jacking. As a result, the project successfully met its objectives for completion and commissioning, delivering high standards, high quality, and high efficiency.