China-Russia East-Route Natural Gas Pipeline Project: The “Power of Siberia” pipeline in Russia has been fully commissioned, with President Putin presiding over the operational launch ceremony.
The Kovykta gas condensate field and the Kovykta–Chayanda natural gas pipeline, located in Russia’s Irkutsk Oblast, were officially commissioned and began delivering gas on the 21st. This marks the completion of the entire Russian section of the Power of Siberia natural gas pipeline, a key component of the China–Russia East-Route Natural Gas Pipeline project.
On the same day, Russian President Vladimir Putin participated via video link in the commissioning ceremony marking the start of operations for the Kovykta gas field and the Kovykta–Chayanda pipeline. He stated that a robust, strategically significant production complex is taking shape in eastern Russia, encompassing natural gas extraction, transportation, and processing. The operation of this complex will provide reliable assurances for supplying natural gas and related products to Russian enterprises and foreign partners, while also giving a strong boost to the socio-economic development of Russia’s eastern regions.
The Kovykta gas field is the largest condensate‑rich gas field in eastern Russia, with recoverable natural gas reserves of 1.8 trillion cubic meters and recoverable condensate reserves of 65.7 million tons. The field is designed to produce 27 billion cubic meters of natural gas annually; its gas is rich in methane, propane, butane, helium, and other components, and is transported via the Power of Siberia pipeline to the Amur Gas Processing Plant, where it supplies a range of natural gas products to consumers. In addition, the Kovykta field produces stable condensate, which can be used to manufacture motor fuel and aviation fuel.
Drilling operations at the Kovyktinskoye gas field commenced in 2019. In October 2022, the field’s No. 2 integrated gas processing unit underwent load‑testing; this facility, which is used for natural gas dehydration and purification, is one of the project’s key priority assets.
The Power of Siberia pipeline was launched in September 2014. With a total length of approximately 3,000 kilometers, it traverses three Russian federal subjects—Irkutsk Oblast, the Republic of Sakha, and Amur Oblast—before reaching the China–Russia border at Blagoveshchensk. Together with the East Route Natural Gas Pipeline, it forms part of the China–Russia East‑Route Natural Gas Pipeline project. In 2019, under the joint witness of the heads of state of China and Russia, Russia began supplying natural gas to China via the Power of Siberia pipeline.
In May 2014, China and Russia signed in Shanghai two key cooperation documents in the energy sector: a Memorandum of Understanding on the East‑Route Natural Gas Cooperation Project between the two governments, and the East‑Route Gas Supply and Purchase Agreement. The two sides agreed that Russia would supply natural gas to China via the East‑Route pipeline, with annual delivery volumes increasing year by year to ultimately reach 38 billion cubic meters per year over a 30‑year period. The primary gas sources are the Kovykta gas field in Irkutsk Oblast, Eastern Siberia, and the Chayanda gas field in the Sakha Republic. Phase I of the pipeline project covers the section from the Chayanda gas field to the China–Russia border, while the pipeline connecting the Kovykta and Chayanda gas fields constitutes Phase II.
The Power of Siberia pipeline project is being implemented by Gazprom. According to reports, the pipeline route traverses complex terrain and harsh climatic conditions. During construction, Gazprom deployed state-of-the-art, highly reliable, and energy-efficient domestically produced technologies and equipment—most notably Russian-made steel pipes with an internal smooth coating, which reduces pipe roughness and friction, thereby lowering energy costs for gas transportation. The outer surface of the pipeline is coated with an innovative domestic nanocomposite material to ensure superior corrosion resistance. Given that the pipeline crosses active tectonic fault zones, Gazprom employed pipes with enhanced capacity to withstand fault‑induced displacement loads and adopted specialized trench‑laying techniques.