The maintenance work on Compressor Unit No. 3 at the Huangjin Gas Compression Station has been successfully completed.
The No. 3 compressor unit at the Golden Compressor Station of the centrifuge project has undergone a major 8,000-hour overhaul. All personnel involved in this maintenance are highly skilled specialists seconded from various departments, with extensive on-site experience in the comprehensive inspection, testing, and commissioning of both domestically produced and imported compressor units.
On the morning of March 21, the作业区 leadership, on-site supervisors, the emergency repair team, and our company’s maintenance personnel convened a briefing meeting. During the meeting, the作业区 leadership underscored the importance of maintenance safety and coordinated efforts among all personnel, providing a detailed explanation of the interlocking relationships among equipment and the corresponding safeguard measures. A dedicated supervisor was assigned to oversee the entire operation and offer assistance, with the goal of achieving the highest possible level of work quality. The project manager emphasized, at the meeting, the safety protocols to be followed before, during, and after the work, as well as potential interlock‑triggering scenarios. He also delineated task assignments for the three specialized teams, clearly defining the scope of each task and outlining appropriate preventive and control measures. Particular attention was paid to ensuring that energy isolation for natural gas, high‑voltage electricity, thermal oil, and valves is carried out in strict accordance with the Energy Isolation Operating Procedures, thereby effectively preventing accidents.

The first impression of major overhauls is often “dirty, disorganized, and substandard.” In this particular overhaul, great attention was paid to addressing these issues: screws removed from machinery, equipment components, oil residues in pipelines, dust accumulated on fan blades, desiccants, jumper wires, oil‑absorbing paper, and waterproof tape stored in electrical distribution cabinets; as well as cable ties removed from control systems, dust inside computers, and replaced defective equipment—all were meticulously sorted, cleaned, and properly stored in accordance with established procedures. Oil‑contaminated materials and used oil‑absorbing paper were transported to the hazardous waste storage area and handled by designated personnel. Replaced faulty equipment was sent to the maintenance workshop for disposal, while rubber mats were laid at the overhaul site, and isolation signs, protective barriers, and warning banners were installed around the units undergoing maintenance.
The instrumentation and control team is a critical component of the entire unit’s overhaul, encompassing the unit control system, emergency shutdown system, communication processing system, as well as related interlock systems such as UCP and UCS. During the maintenance, all identified issues were thoroughly resolved, and similar problems on the other two units were addressed in parallel, thereby alleviating the customer’s concerns. For frequently encountered issues—such as safety barriers for vibration probes, proper positioning of temperature probe measurements, overheating of control cards, and poor contact—the instrumentation and control team conducted rigorous testing and calibration to meet specified standards, and also resolved problems like industrial PC crashes and erroneous numerical displays.

The electrical team serves as the prerequisite for any maintenance work; all electrical equipment must undergo a series of safety procedures before servicing, including obtaining the necessary permits, de-energizing, installing grounding wires, posting warning signs, and locking out the equipment. “There are no small matters when it comes to safety” — this principle is firmly ingrained in the minds and practices of all maintenance personnel. The electrical team’s primary maintenance tasks include comprehensive inspections of variable-frequency drives, phase-shifting transformers, air coolers, lubrication oil pumps, and other electric motors, along with testing key components and recording actual measured values. During operations, numerous non‑conformities were identified and addressed, with each issue reported and resolved systematically. In particular, testing and calibrating the temperature‑and‑humidity sensors on the variable-frequency drives proved time‑intensive; through meticulous and repeated measurements, accurate readings were ultimately obtained.
The mechanical team bears the heaviest workload of all maintenance operations, yet they are the first to complete their tasks. Undaunted by hardship or fatigue, they proactively advance the overhaul project and, in response to numerous compressor-related issues, collaborate closely with the plant site to devise the most appropriate solutions. Guided by the principle that “alleviating our customers’ concerns is also alleviating our own,” they have not only resolved problems affecting other units but have also proposed optimal workarounds for those that cannot yet be addressed.
“Diligence brings spring early, and practical action is the right moment.” The overhaul of Compressor Unit No. 3 has been successfully completed, yet the Purihaote team’s drive for progress shows no sign of slowing. All employees will remain committed to their roles, strive to excel, and continue to strengthen equipment reliability, laying a solid foundation for the safe and stable operation of the unit during peak summer demand.